No Comments

Leviathan gas platform embarks on 11,500 km. journey to Israel – The Jerusalem Post

Leviathan gas platform embarks on 11,500 km. journey to Israel – The Jerusalem Post


X

Dear Reader,

As you can imagine, more people are reading The Jerusalem Post than ever before.
Nevertheless, traditional business models are no longer sustainable and high-quality publications,
like ours, are being forced to look for new ways to keep going. Unlike many other news organizations,
we have not put up a paywall. We want to keep our journalism open
and accessible and be able to keep providing you with news
and analysis from the frontlines of Israel, the Middle East and the Jewish World.

As one of our loyal readers, we ask you to be our partner.

For $5 a month you will receive access to the following:

  • A user experience almost completely free of ads
  • Access to our Premium Section
  • Content from the award-winning Jerusalem Report and our monthly magazine to learn Hebrew – Ivrit
  • A brand new ePaper featuring the daily newspaper as it appears in print in Israel

Help us grow and continue telling Israel’s story to the world.

Thank you,

Ronit Hasin-Hochman, CEO, Jerusalem Post Group
Yaakov Katz, Editor-in-Chief

UPGRADE YOUR JPOST EXPERIENCE FOR 5$ PER MONTH

Show me later

The first of four giant barges transporting the Leviathan natural gas platform to Israel departed the Gulf of Mexico last week, the companies leading the project announced on Sunday, ahead of its September installation approximately 10 km. off Israel’s coast.

Five operational structures – the 38,000-ton topsides of the Leviathan platform – will make the approximately 11,500 km. trans-Atlantic journey, with the remaining barges due to set sail from Texas in the coming weeks.

The structures will be installed on top of the platform jacket by the largest offshore crane in the world, with the jacket – or foundations – lowered into the Mediterranean Sea in January. The installation will take approximately four weeks to complete.

The topsides will house the platform’s gas processing facilities, worker accommodation, work areas, helipad and platform operation facilities, including power generation, water desalination and waste treatment.

The topsides are 102 m. long, 80 m. wide and will stand 47 m. above sea level. The platform flare boom, permitting the safe burning of gas, will stretch to 130 m. above sea level.

Once assembled, project partner Noble Energy will commence a series of commissioning tests prior to initiating commercial gas flow before the end of 2019 to the Israeli market, and subsequently to neighboring countries.

Delek Drilling, Noble Energy and Ratio Oil Exploration have invested $3.75 billion in the development of the Leviathan Reservoir since its discovery in 2010.

One of the largest discovered worldwide in the last decade, the reservoir is expected to contain up to 605 billion cu.m. of natural gas, equivalent to 65 years of domestic gas consumption.

In addition to domestic supply, Israel is also due to become a significant energy exporter to its neighbors.

In February 2018, Delek Drilling and Noble Energy signed a $15b. decade-long deal to supply 64 billion cu.m. of natural gas to Egypt from the Leviathan and Tamar gas fields, with the latter already supplying natural gas to Israel since 2013.

Once the Leviathan field commences operations, the partners expect to sell at least 9.91 million cu.m. of natural gas per day to contracted customers in Egypt. Initial gas delivery through the EMG pipeline linking the Israeli and Egyptian networks is expected to occur from the Tamar field.

The deal with Egypt follows a Septemb